What is a task dependency?
A link between two tasks that says one can't start (or finish) until the other does.
A task dependency records that one piece of work waits on another. There are four classic types:
- Finish to start: B can't start until A is finished. This is by far the most common (copy before design, design before build).
- Start to start: B can't start until A has started.
- Finish to finish: B can't finish until A has finished.
- Start to finish: B can't finish until A has started. Rare.
Dependencies make a schedule honest: when one task slips, you can see exactly which tasks slip with it.